The Arizona Department of Transportation (ADOT), working together with the town of Payson, is planning a modern roundabout at State Route (SR) 87 and Airport Road.
ADOT is in the very early stages of design and has presented this information to the elected leaders in Payson and residents of Payson.
The final design won’t be complete until late 2008; environmental clearances will be done in late 2008; right of way acquisition will be complete in early 2009; with construction beginning in summer of 2009 and completed by fall of 2009. The town and ADOT are sharing the cost of the roundabout.
Project Details
Select a map below to view a larger version.